Cincinnati's Abandoned Subway
Introduction Abandoned tunnels are often the object of urban legend, but Cincinnati is in fact the site of the country's largest abandoned subway tunnel. But "abandoned" is not quite the word, as construction slowed to a stop in 1925 before even half of the 16 mile line was completed. Seven miles between Cincinnati's central business district and the industrial suburb of Norwood were tunneled, bridged, or graded, but no track was laid and no subway cars were ordered. No passengers ever rode between the six stations that were built.
The incomplete Cincinnati line sat fallow through the Great Depression and WWII. Bridges, stations, and retaining walls along the surface stretches deteriorated to such an extent that a few items actually collapsed. Nearly everything above ground was bulldozed to make way for portions of I-75 and the Norwood Lateral in the 1950's and 1970's, respectively. The mute two mile tunnel that remains under Central Parkway is unknown to many Cincinnati natives, and what most who do know of it know consists largely of hearsay and speculation.
This page is the most comprehensive and most accurate source of information regarding the subway either on the web or in print. It is by far the most popular subject on www.cincinnati-transit.net, and tens of thousands have visited it since its appearance in 1999.
Subway F.A.Q.
1. Where is the subway? The main subway tunnel runs under Central Parkway for two miles, between Walnut St. and an anonymous spot north of the Western Hills Viaduct. Three underground stations were built and still exist at Race St., Liberty St., and Brighton's Corner. An extension of this tunnel under Walnut St. south through downtown with a station at Fountain Square was planned but never built. Additionally, several miles of surface running line were graded and three of roughly a dozen planned above ground stations were built. Significant portions of today's I-75 and the Norwood Lateral follow the path of the line. A stretch of I-71 near the Dana Ave. interchange was built where the subway loop's eastern half was planned.

2. When was it constructed? 1920 through 1925. The $6 million bond issue in 1916 was exhausted in 1925, no further money was obtained, and construction never resumed.
3. Can the tunnel still be used? Yes. It has been continuously maintained and will likely be usable for the next hundred years, if not longer. The 2002 "Metro Moves" sales tax would have funded a rail transit network that planned to use the tunnel, but it was defeated by a 2-1 public vote.
4. Can the subway be visited? Yes. See http://www.cincinnatiadvance.com. I am in no way involved with that organization nor do I have anything to do with the tours. Do not email me about the tours -- I have never been on one and haven't been in the subway since 2002. No, I don't know when they're next one is.

Section 1 Planning and construction Section 2 Completion attempts Section 3 The subway today Section 4 Various proposals Section 5 What might have been Section 6 Future use